Please note: This is a high-level, recommended list of basic items, not a comprehensive checklist for seasoned owners or developers. It came out of a conversation with a first-time SBA borrower preparing to collect bids from general contractors, and we thought the topics were worth sharing with others in the same position. Every project is different, and specific circumstances (project size, location, lender or loan program requirements, contract terms, owner preferences) may require different procedures than those described here. Always confirm requirements with your lender, attorney, and design team before finalizing your bid package. This article is informational only and is not legal advice.
First-time borrowers often assume the bid package is just drawings and a request for a number. The bid package is where you set the rules for the entire project. Whatever you leave out, the GC will fill in with their own preferences, and you’ll be negotiating from behind. This is especially true on a lender-financed project with funds control, where the GC’s administrative habits matter as much as their field work.
Here’s what we recommend covering before the package goes out:
1. Pick the contract type up front
For most small to mid-size projects, ask for a stipulated sum (fixed price) contract rather than cost-plus. It gives you cost certainty and makes draws simpler to administer.
We recommend the standard AIA contract forms. They’re the most widely used; they come with a built-in change order process, retainage section, and liquidated damages provision, and any experienced GC will know them. Some contractors prefer their own forms. That’s their right, but think hard before agreeing, because you lose the protections and familiarity of an industry standard.
2. Require a real schedule of values
Don’t accept a lump sum. Require the bid broken down line by line, ideally by CSI MasterFormat division, so it can be evaluated against your budget and tracked through construction. That same breakdown becomes the backbone of every pay application.
3. State your retainage terms
If you don’t specify retainage, the GC will, and they might write 5%, 0%, or something else. 10% is a common standard, though requirements vary by state and lender, so check your loan documents.
Retainage is the portion held back from each invoice (10% of a $100,000 invoice means $10,000 held). It protects you if subs are unpaid or work is substandard, and it creates leverage for punch list and closeout. It’s released once the GC delivers closeout documents such as the certificate of occupancy.
In the AIA form, you can list exclusions from retainage. Our advice is to exclude nothing. A GC may push back on retainage for up-front costs like insurance, and you can negotiate that when it comes up.
4. Spell out draw procedures
Tell bidders how they’ll get paid before they bid. Each pay application should include:
- AIA G702/G703 (the application and continuation sheet showing budget, previously billed, currently billed, remaining, percent complete, and retainage by line)
- Backup invoices from subs and suppliers
- Lien waivers from the GC and every sub
On a funds-controlled loan, a GC can’t simply say “the drywall sub needs $100,000.” They need to show the invoice and a lien waiver, so the lender can confirm that the people being paid have actually been paid, with no potential liens on the property.
Tell GCs early if the project is lender-financed, and especially if it’s an SBA loan, which can be audited by the federal government. GCs used to working directly with owners and paying subs on a handshake sometimes struggle with this paperwork. Better to find out during bidding than after you’ve signed.
A simple screening test: mention “lien waivers” to each bidder. Lien waivers are standard industry practice, and a GC should already be collecting them from their own subs. If they look at you blankly, treat it as a red flag. Lien waivers protect you, and they protect the GC too.
5. Control change orders
Change orders are where budgets get blown. The standard AIA language requires the GC to get written approval from the owner. On a financed project, add a line requiring lender approval of every change order before the owner signs it.
This matters for two reasons. It prevents the “we talked about it and you said yes” problem, since approval has to be written. And with some loan programs, a change that increases the budget can require a use-of-proceeds amendment and a new credit memo, which is a lengthy process. The fewer change orders, the better.
6. Define the start date and completion date carefully
If you ask for “120 days,” the obvious question is: from when? We suggest tying the start date to the latest of three events:
- Permits in hand
- Financing closed
- Written notice to proceed from the owner
Give the GC a short window (for example, seven days) after the notice to proceed to mobilize. That starts the clock and sets the completion date, which should be defined as substantial completion and certificate of occupancy. After that, the completion date should only change by change order, and the GC must justify any delay in writing.
Pinning down both dates is what makes the next item enforceable.
7. Consider liquidated damages
Liquidated damages are a daily charge if the project is delivered late. The AIA contract has a section for it. The amount should be reasonable and tied to your actual cost of delay, such as lost revenue per day of not being open. It’s a deterrent, not a punishment. Set it too high and good contractors won’t bid
Many contractors will ask to cap it at the amount of their fee, and as a practical matter, deductions often come out of the fee at the end of the job.
8. Ask for a milestone schedule
Request a one-page schedule showing the major phases: underslab plumbing, framing, rough-ins, drywall, finishes, inspections, closeout. It doesn’t need to be detailed, but it should be more than “start” and “finish.” A schedule helps you hold the GC accountable early, when “drywall was due February 1st” is a much easier conversation than discovering you’re three weeks behind. Pair it with a weekly status check-in.
9. Confirm insurance requirements
The GC will need to carry their own coverage, including builder’s risk for the duration of the project. Your lender will have specific requirements, so get those from them before the package goes out and include them in the bid instructions.
10. Publish a clear bid timeline
Give bidders firm dates for:
- Invitation to bid
- Deadline for written questions
- Final addendum
- Bid due date
- Anticipated GC selection
- Construction commencement (tied to the start-date language above)
Also confirm where you are in plan approvals and permitting (landlord, local code review, any special agency approvals), since open items there can affect bids and schedule.
Bottom Line
The bid package should answer, in writing, the questions you’d otherwise argue about later: what kind of contract, how they’ll be paid, what backup is required, how changes are approved, when the clock starts, and what happens if it runs late. Borrowers who set these expectations before selecting a GC are far ahead of most, and they end up with contractors who are comfortable with the process the loan requires.
If you’re preparing a bid package for a financed project and want a second set of eyes before it goes out, reach out to our team.